Fischbeker Heidbrook

  • September 2022

    Concluding ceremony with Hamburg's First Mayor Dr. Peter Tschentscher, among others

  • June 2019

    Start of e-carsharing

  • December 2018

    Completion of playgrounds and open spaces north of the Uwe-Seeler sports hall

  • October 2018

    Reopening of the Uwe-Seeler sports hall

    • Enlarge image
  • August 2018

    Bus line starts up through the district

  • July 2018

    Local suppliers open

  • August 2017

    Site celebration for residents

    • Enlarge image
  • Autumn 2016

    Start of vertical construction

  • 2016

    Start of marketing for detached and semi-detached plots in phase of construction II

  • 2015/16

    Initial development works

  • Early 2015

    Start of marketing for detached and semi-detached plots in phase of construction I

  • 2014

    Expert assessment procedure for construction on the Plateau

  • 2014

    Designation of the area of the former Röttiger Kaserne in Fischbeker Heidbrook and development of the communication design and campaign “Living close to nature”

  • 2013/14

    Creation of the functional plan

  • January 2013

    Commission from the Hamburg Senate for the IBA Hamburg to develop the project