In the Wilhelmsburger Rathausviertel (Wilhelmsburg Town Hall District)

  • October 2024

    Preliminary approval and adoption of the draft development plan

  • July 2022

    Concept phase of the expression of interest procedure for building cooperatives in Wilhelmsburg

  • January 2022

    Start of geothermal drilling

  • November 2021

    First letter of interest for building cooperatives in Wilhelmsburg.

  • October 2019

    Closure of the old Wilhelmsburger Reichsstraße and start of dismantling works on the southern part.

  • Since 2016

    Development of the functional plan (further development of the design, more in-depth coverage of certain special topics like traffic, drainage, open space etc.)

  • 9 December 2015

    Judges decide on the design by De Zwarte Hond + RMP Stephan Lenzen Landschaftsarchitekten, Rotterdam/Cologne/Hamburg

  • December 2015

    Public final presentation

  • September 2015

    Public design workshop

    • Enlarge image
  • September 2015

    Start of the urban/open space planning competition “Housing for all – in the centre of Wilhelmsburg”

  • April 2015

    First public informational event